OWNER: Florida Department of Transportation, District 5
VALUE: $ 67.8 million
ENGINEER: H.W. Lochner
YEAR COMPLETED:  Ongoing

During this 950-day, $67.8 million project, Prince is widening and reconstructing SR 50 from E of Dean Road to E of Avalon Park Boulevard from a four-lane rural roadway to a six-lane urban divided highway. Project improvements include construction of curb and gutter, 275,000 square yards of aggregate base and flexible pavement, nearly 70,000 linear feet of storm sewer including over 400 drainage structures, replacement of box culverts, signing and pavement markings, and signalization. JPA work includes over 47,000 linear feet of large diameter water and sanitary force main construction.