Poinciana Boulevard

By the conclusion of this $6.2 million project, we constructed 2.5 miles of new roadway as well as milled & resurfaced 2.5 miles of existing roadway.

Read More...
heavy-highway
SR 17 (10th St. S.) Polk County

This 600-day, $7.9 million project encompassed 1.5 miles of complete urban roadway reconstruction of SR 17, from SR 544 (Scenic Highway) to US 17 (Hinson Avenue).

Read More...
heavy-highway
US 301/Tampa Bypass Canal to Fowler

This 800-day, $21.4 million project consisted of the reconstruction of US 301 from a two-lane roadway to a four-lane divided roadway for 1.9 miles from just south of Raulerson Ranch Road to just north of Bradley Road.

Read More...
heavy-highway
I-275/SR 93 Hillsborough County

During this 750-day, $29 million project, Prince widened and rehabilitated over three miles of roadway as well as sixteen bridges, including the bridge that spans the Hillsborough River.

Read More...
heavy-highway
I-275 Tampa

During this 20-month, $20.4 project, Prince widened I-275 in Tampa, Florida from its intersection with US 41 to the I-75/I-275 interchange.

Read More...
bridges,heavy-highway
I-75 Tampa (SR 56 to S. Fowler)

During this 1500-day, $94.7 million job, Prince widened and reconstructed 11.4 miles of I-75 through Tampa, Florida, including replacement of 3 bridges, widening of 16 bridges, construction of an Acrow temporary bridge, and installation of 85,000 LF of storm drainage.

Read More...
heavy-highway
North Cattlemen Road

During this 540-day, $14.5 million project, Prince widened the two-lane section of the existing roadway to four lanes and extended the four-lane roadway section north to DeSoto Road.

Read More...
heavy-highway
US 301 Hillsborough County

The US 301 project commenced on November 17, 2008 and consisted of widening US 301 from two lanes to six lanes for a six mile stretch of highway between Gibsonton Drive and CR 672 in Hillsborough County for The Florida Department of Transportation.

Read More...
bridges,heavy-highway
Boyette Road Phase III

During this 43 month, $22 million project, Prince  built four signalized intersections, water and sewer services, and constructed a new bridge...

Read More...
heavy-highway
SR 408 Oxalis Drive to Goldenrod Road

During this 17-month, $20.8 million project, Prince widened .8 miles of the existing toll road and two bridges, constructed numerous retaining walls, and installed aesthetic treatments on structural elements throughout the site.

Read More...
heavy-highway
Innovation Way

Prince completed the construction of Innovation Way, a new, 4-lane, urban roadway, five months ahead of schedule.

Read More...
heavy-highway
I-595 Segments A & B

Prince reconstructed SR84, widened I-595, and constructed reversible express lanes along 4.3 miles of the I-595 Express Project Corridor, beginning at the I-595/I-75 Interchange...