SR 429 Wekiva Parkway from US 441 to North of Ponkan Road

During this 660-day, $56.2 million project, Prince will construct SR 429 (Wekiva Parkway) from US 441 to north of Ponkan Road in Orange County, Florida.

Read More...
heavy-highway
SR 15 (Hoffner Road)

During this 1300-day, $37.1 million project, Prince will widen and reconstruct 3.811 miles of SR 15 (Hoffner Ave.) from Lee Vista Boulevard to Conway Road in Orange County, Florida.

Read More...
heavy-highway
SR 50 from Dean Road to E of Avalon Park Blvd., Orange & Brevard Counties

During this 950-day, $67.8 million project, Prince is widening and reconstructing SR 50 from E of Dean Road to E of Avalon Park Boulevard from a four-lane rural roadway to a six-lane urban divided highway.

Read More...
heavy-highway
Bruce B. Downs (CR 581)

This 3.55-mile, $36,148,000 project to reconstruct a four-lane rural roadway to an eight-lane urban roadway will last for 815 days. Other work includes widening the southbound Cypress Creek Crossing bridge from two lanes to four, and constructing a brand new four-lane northbound bridge.

Read More...
heavy-highway
Poinciana Boulevard

During this 304-day, $6.2 million project, Prince will construct 2.5 miles of new roadway as well as mill & resurface 2.5 miles of existing roadway. Three new stormwater retention ponds will be constructed along with a 123 foot single-span pedestrian bridge. Polyester polymer concrete overlay will be applied on the two existing roadway bridges.

Read More...
heavy-highway
SR 17 (10th St. S.) Polk County

This 600-day, $7.9 million project encompasses 1.5 miles of complete urban roadway reconstruction of SR 17, from SR 544 (Scenic Highway) to US 17 (Hinson Avenue).

Read More...

This 800-day, $21.4 million project consists of the reconstruction of US 301 from a two-lane roadway to a four-lane divided roadway for 1.9 miles from just south of Raulerson Ranch Road to just north of Bradley Road.

Read More...
heavy-highway
I-275/SR 93 Hillsborough County

During this 750-day, $29 million project, Prince widened and rehabilitated over three miles of roadway as well as sixteen bridges, including the bridge that spans the Hillsborough River.

Read More...
heavy-highway
I-275 Tampa

Prince is widening I-275 in Tampa, Florida from its intersection with US 41 to the I-75/I-275 interchange. The 20-month project consists of widening 6.0 miles of the existing interstate from four to six lanes.

Read More...

During this 1500-day, $94.7 million job, Prince is widening and reconstructing 11.4 miles of I-75 through Tampa, Florida, including replacing 3 bridges, widening 16 bridges, constructing an Acrow temporary bridge, and installing 85,000 LF of storm drainage.

Read More...
heavy-highway
North Cattlemen Road

During this 540-day, $14.5 million project, Prince widened the two-lane section of the existing roadway to four lanes and extended the four-lane roadway section north to DeSoto Road.

Read More...

The US 301 project commenced on November 17, 2008 and consisted of widening US 301 from two lanes to six lanes for a six mile stretch of highway between Gibsonton Drive and CR 672 in Hillsborough County for The Florida Department of Transportation.