Prince will widen SR 821 (HEFT) from the Florida Turnpike to south of Miramar Parkway, in Miami-Dade (87471) and Broward (86471) Counties in this 1,430-day project.
Read More...This 1,115-day, $52.3 million project, consists of ramp alignments and add capacity at the SR 93A (I-75) and SR-60 interchange in Hillsborough County, FL.
Read More...This 745-day project reconstructed the interchange at University Parkway and I-75, replacing the existing interchange with a diverging diamond interchange.
Read More...The project includes converting the existing High Occupancy Vehicle (HOV) lanes to High Occupancy Toll (HOT) lanes, as well as one lane widening each direction, resulting in two tolled express lanes in each direction.
Read More...This 1,050-calendar day project widens a two and one-half mile section of highly traveled urban arterial roadway in Orlando, Florida
Read More...The Project includes the design and construction necessary to convert the existing High Occupancy Vehicle (HOV) lanes to Managed Lanes in both the northbound and southbound directions of a 7.4-mile section of I-95 from north of Commercial Blvd to south of SW 10 St in Broward County, FL.
Read More...During this 1500-day, $94.7 million job, Prince widened and reconstructed 11.4 miles of I-75 through Tampa, Florida, including replacement of 3 bridges, widening of 16 bridges, construction of an Acrow temporary bridge, and installation of 85,000 LF of storm drainage.
Read More...This 795-day, $54.1 million project provided a new direct connection from I-75 to the Mid-Field Terminal facilities of the Southwest Florida International Airport (SWFIA.)
Read More...During this 43 month, $22 million project, PrinceĀ built four signalized intersections, water and sewer services, and constructed a new bridge...
Read More...Prince constructed a new four lane bridge over I-75 that connects New Tampa Boulevard to Commerce Park Boulevard. The architectural elements of the bridge create a gateway...
Read More...