OWNER: Florida Department of Transportation, District 7
VALUE: $ 52.3 million
YEAR COMPLETED:  Ongoing

This 1,115-day, $52.3 million project, consists of ramp alignments and add capacity at the SR 93A (I-75) and SR-60 interchange in Hillsborough County, FL.  A total of six bridges will be remediated throughout construction; three new bridges will be constructed, one bridge will be widened, and two bridges will receive a deck replacement.  Other key elements of this project include 76,143 SY of 12” thick concrete paving, 190,138 SY of MSE wall, 225,787 CY of embankment, sound walls, and extensive improvements to the lighting of the interchange.