OWNER: Florida Department of Transportation
VALUE: $43 million
ENGINEER: Pitman-Hartenstein & Associates, Inc.
YEAR COMPLETED: 2010

During this 1027-day, $43 million project, Prince completely reconstructed 3.6 miles of Causeway Boulevard from US 301 to US 41. The existing two lane roadway was removed and Prince constructed a four-lane urban roadway with two separate drainage systems, four signalized intersections, and new watermain and forcemain throughout the project. This project finished on contract day 660, 367 days ahead of schedule.